Data Migrator - How to schedule process flow to run on a daily for 15 times every 4 minutes so I can process 300 records (15 x 20 records)?

In the Schedule Object I selected the following but it didn't run:
1) Specify a Schedule Type of Recurring.
2) Select an Interval Type of Minutes.
3) Select an Interval Value of 4
4) Select Start Date of 11/01/2011
5) Select Start Time of 15:25
6) Select End Date of 11/02/2015
7) Select End Time of 09:00
8) Select Intraday Start of 15:25
9) Select Intraday End of 16:25

Please help.

Thanks,
Ric

Prod/Dev: Data Migrator version 7.7.03/Win 2003/32 bit


WF 7.6.8
Windows NT
Excel, PDF, HTML
November 02, 2011, 01:10 PM
Ric
NOTE:

The Schedule Object I selected is working properly now. This request is fixed already. Thanks.


WF 7.6.8
Windows NT