Anybody is using parallel group? We are having problems with the WAIT object after a parallel group. We were told to put a very high value for the WAIT object, and the flow will continue after
the last process flow in parallel is completed. But
it looks like the process keep waiting forever.
 
Posts: 2 | Registered: November 14, 2005Reply With QuoteReport This Post
Platinum Member
posted Hide Post
We are using parallel groups without any problem. My wait is set to 0 which means the next process is triggered after all the parallel groups complete. We are at 7.1 on USS.


WF7.1.4 Prod/Test, MRE, self serve, DM
 
Posts: 176 | Location: Desplaines | Registered: August 05, 2004Reply With QuoteReport This Post