Focal Point
Run Flow in Defered mode

This topic can be found at:
https://forums.informationbuilders.com/eve/forums/a/tpc/f/1381057331/m/8741046072

February 08, 2008, 05:33 PM
Kar
Run Flow in Defered mode
Hi,
I not able to run a flow (.fex) in Defered Mode from Data Management Console.

When I select a flow to be run in Defered Mode from DMC, it shows the status of Queueing in the Web Console but is never kicked off.

If the similiar flow is run in Defered Mode from WebConsole, it kicks off and status changes from Queueing - Executing - Ready.

Kar
Data Management Console Release 720
February 09, 2008, 11:32 AM
Jessica Bottone
The first thing that came to mind was the Scheduler. While you've not actually 'scheduled' anything, it is involved when running things deferred. When I've had issues getting flows to run deferred, it was because the scheduler had crashed so check that. The other thing to check is your log file. If I'm remembering correctly, there is a 2gb limit. If it fills up, it can make it appear that your job didn't run but it really did. You just can't get any logs to tell you that it did actually run. :-) If it's full, re-create it. Good Luck.


Data Migrator 5.3, 7.1, 7.6
WebFOCUS 7.1, 7.6, 7.7
SQL Server, Oracle, DB2