Hi,

We are using wf 7.6.1.
Everything is running on the same server. I mean the wf client the webfocus reporting server...
I tried to schedule a job and it fails with the following error:


Job Description: majid now

User: admin
Procedure: J12g4ornvi02
Schedule ID: S12g4or9p001
Start Time: 2007-07-27 11:21:06 PM
End Time: 2007-07-27 11:21:06 PM
Starting worker thread
Error connecting to the WebFOCUS Reporting Server EDASERVE: EDA SQL STATUS (-30)
Starting task: Task 1
Task type: EDA RPC
Procedure name: plantstd_report/edfax1
Connecting to server EDASERVE with execution id v2agent
Task error:Server disconnected, cause 32008 Eda state -30
No report to distribute.

Could somebody help solving it.

Thanks .


WebFocus 7.6.5
AND WebLogic server as web server
sql2005 as database server
July 28, 2007, 06:03 AM
FrankDutch
Did you search on the IBI tech support for the specific error code?
Is the service RC running?
How about password settings, RC must be a user as far as I know.




Frank

prod: WF 7.6.10 platform Windows,
databases: msSQL2000, msSQL2005, RMS, Oracle, Sybase,IE7
test: WF 7.6.10 on the same platform and databases,IE7

July 28, 2007, 03:27 PM
FortuneCookie
The -30 indicates an invalid protocol.

Can you get MR to work under your config? If the message is correct that may fail as well.


Prod: WebFOCUS 7.1.6, Windows 2003

Dev: WebFOCUS 7.6.2, Windows 2003