I am setting up a new RC job with multiple tasks that needs to run on the fifth business day of the month. If I am using &&KILL_RPC to stop a process do I need to add it to every task? Is it better to use a preprocessing routine or to add the code to the program?
Here's the solution ===>
I set up a couple programs and tested them in Report Caster. What I found was that the &&KILL_RPC routine needs to be a preprocessing routine rather than an -INCLUDE in the program and that every task requires it. When I put it in only one task, my second task still ran. When I added the code to the progam, the program still executed.This message has been edited. Last edited by: PBrightwell,
Pat WF 7.6.8, AIX, AS400, NT AS400 FOCUS, AIX FOCUS, Oracle, DB2, JDE, Lotus Notes
April 30, 2010, 03:02 PM
Kerry
Thanks Pat for sharing the info with all.
Cheers,
Kerry
Kerry Zhan Focal Point Moderator Information Builders, Inc.