Hi,

Recently We have Report Caster, because of problems it can occur that the database is filled later than normal. Is it possible to make a scheduler task dependence on the database.

This message has been edited. Last edited by: <Emily McAllister>,
 
Posts: 103 | Registered: March 18, 2008Reply With QuoteReport This Post
Virtuoso
posted Hide Post
What you can do is to use the Alert feature. Which is one of the solutions.

The way Alert works is first testing a condition and if the condition is true then execute something else otherwise do nothing.

Creating an Alert


WF versions : Prod 8.2.04M gen 33, Dev 8.2.04M gen 33, OS : Windows, DB : MSSQL, Outputs : HTML, Excel, PDF
In Focus since 2007
 
Posts: 2264 | Location: Montreal Area, Qc, CA | Registered: September 25, 2013Reply With QuoteReport This Post
Platinum Member
posted Hide Post
Martin,

Thanks for your reply I will look at it.
 
Posts: 103 | Registered: March 18, 2008Reply With QuoteReport This Post