December 10, 2008, 02:10 PM
cbradyLoading Measures Frequency
We have some operational measures that are updated hourly. I'd like to schedule these - but there is no option in the scheduler beyond once per day. How would I accomplich this?
December 10, 2008, 02:47 PM
Michael PaulThe PMF scheduler communicates with ReportCaster on the backend to execute the actual loads.
There are further details you can set for the PMF schedules by going directly into ReportCaster to modify the created schedule. Just open ReportCaster and find the “Job Description” that matches the name of the schedule you setup from within PMF. Open this schedule and you can change the “Run Interval” to “Hour(s)” and click OK.
The PMF load frequency should then match what you are looking to do.
Good luck!
Mike