Focal Point
Schedules

This topic can be found at:
https://forums.informationbuilders.com/eve/forums/a/tpc/f/7971057331/m/1531058331

April 22, 2005, 03:37 AM
<Amy Goll>
Schedules
I have a scheduled created for a report to run daily. It will run for a day or two then it stops. When I try to open the schedule to find out the problem I get the following error:

There is no packet data retrived for the specified schedule.

The other schedules have been running correctly.

Thanks.
April 22, 2005, 12:45 PM
Prarie
Somehow your schedule has become corrupted or is missing something. Have you tried just deleting and starting over?
April 23, 2005, 09:21 PM
susannah
always say what verion you are in. e.g. version 4 is very dif from verion 5. Have you checked the box 'delete schedule after run'? , by any oddball chance?