I want to schedule a job on the first business day of the month, is that possible?




Frank

prod: WF 7.6.10 platform Windows,
databases: msSQL2000, msSQL2005, RMS, Oracle, Sybase,IE7
test: WF 7.6.10 on the same platform and databases,IE7

February 01, 2007, 02:03 PM
susannah
hmmm, what an intersting question...
the hard way...
i would schedule the job on a daily basis and have a pre-processing fex to determine whether to kill it or not.
or...
i would schedule 4 jobs on a monthly basis on days 1,2,3,4, 5,and use that same pre-processing fex.. (5 because we have some 4-day weekends here..)




In Focus since 1979///7706m/5 ;wintel 2008/64;OAM security; Oracle db, ///MRE/BID
February 01, 2007, 02:07 PM
FrankDutch
Yes Susannah that is the hard way, but that also brings a kill process every day and an error report in my mailbox...
I have to ask for a change by webfocus
A few new options:
First business day per month.
First business day per week.
the same for the last BD per week and month.




Frank

prod: WF 7.6.10 platform Windows,
databases: msSQL2000, msSQL2005, RMS, Oracle, Sybase,IE7
test: WF 7.6.10 on the same platform and databases,IE7

February 01, 2007, 02:58 PM
RichH
Hi Frank,
It's in WF 76. The monthly schedule interval has been enhanced to allow you to schedule a job every nth day of the week every n months (for example, the first Monday every 2 months), or on
specific days every n months.
Rich


WebFOCUS 8202 Win 2012
Test - WebFOCUS 8203 on Win 2012
February 01, 2007, 04:21 PM
Prarie
That is good news.


In Focus since 1993. WebFOCUS 7.7.03 Win 2003