Hi, I have a schedule with two task, say task1 and task2. I want RC to execute the task2 only if task1 is successful.
Please suggest some thoughts..
Regards, VivekThis message has been edited. Last edited by: jvb,
WF 8.1.04,Infoassist,Oracle, Excel, PDF,HTML.
February 04, 2015, 02:08 AM
Ram Prasad E
Search for &&KILL_RPC in this forum. You will find more discussions on this topic.
At highlevel, You need to use same logic used in task1 in pre-process and assign 'Y' to &&KILL_RPC variable if the logic fails. Default &&KILL_RPC to 'N'.
This is a good idea. For my client I had to create a log table that has this information and more. We use this data to display reports and graphs on the portal to the business partners in real time (refresh every 10 mins).