Focal Point
Auto start failed caster job

This topic can be found at:
https://forums.informationbuilders.com/eve/forums/a/tpc/f/7971057331/m/3711015542

September 05, 2007, 08:25 PM
dballest
Auto start failed caster job
Is there a setting in Reportcaster that would automatically restart the job if it fails to execute properly on the scheduled time?

Thanks,
Dan


Dev: WebFOCUS 7.6.10, Data Migrator 7.6.10
QA: WebFOCUS 7.6.10, Data Migrator 7.6.10
Prod: WebFOCUS 7.6.2, Data Migrator 7.6.8
Windows 2K3, Tomcat 5.5.17, IIS 6
Usage: HTML, PDF, Excel, Self-serve, BID and MRE
September 06, 2007, 10:08 AM
hammo1j
Sorry Dan

Why would you want this - surely it would fail again on the restart...



Server: WF 7.6.2 ( BID/Rcaster) Platform: W2003Server/IIS6/Tomcat/SQL Server repository Adapters: SQL Server 2000/Oracle 9.2
Desktop: Dev Studio 765/XP/Office 2003 Applications: IFS/Jobscope/Maximo
September 06, 2007, 01:11 PM
dballest
hammo1j,

These past few days we have some network issues accessing the web services. The job/fex is okay, it's the connection that failed. It could be a coincidence that at that particular moment, the connection failes but after a few minutes all is fine. I want it to try to run again until it runs successfully.

It is also because we've schduled it to run very early in the morning and no support will be on-site until a few hours after the report runs.

Dan


Dev: WebFOCUS 7.6.10, Data Migrator 7.6.10
QA: WebFOCUS 7.6.10, Data Migrator 7.6.10
Prod: WebFOCUS 7.6.2, Data Migrator 7.6.8
Windows 2K3, Tomcat 5.5.17, IIS 6
Usage: HTML, PDF, Excel, Self-serve, BID and MRE