Can a scheduled task be set up to trigger subsequent tasks concurrently? Currently, I have a single job that runs prior to 10 concurrent extracts.

When they run successfully via overnight scheduling, everything is fine, but if something fails, I have to manually run the first job, wait for it to finish, then manually submit the 10 extract jobs one by one.

Is there a way that I could do this just by submitting the first job manually, to act more like a CA7 schedule, and to add to the elegance, could I also trigger a task that would not start running until those 10 concurrent tasks are completed?
January 25, 2006, 10:21 AM
Kerry
Hi InsideTGT,

Has this issue been resolved?

There is an article on our Focus on Developers may be of interest:

How to Automatically Delay ReportCaster Jobs: Sometimes data loads take longer than planned. Jodye Yates explains how to delay report distribution in 10-minute increments.

Is this what you are trying to do?

Hope this helps.

Cheers, Smiler

Kerry


Kerry Zhan
Focal Point Moderator
Information Builders, Inc.
January 25, 2006, 10:42 AM
InsideTGT
Thanks, Kerry. I didn't get any other replies, so this may be the way to go. I'll print off the article and run with it.